PT ADARO MINERALS INDONESIA TBK 1H23 ACTIVITIES REPORT
Mr. Christian Ariano Rachmat, President Director and CEO of PT Adaro Minerals Indonesia Tbk
said:
“Higher production and sales volume in 1H23 reflect market recognition and acceptance
of our high-quality product supported with solid operations. We are on track to achieve
FY23 guidance and execute our projects, in both metallurgical coal and aluminum smelter.
Securing financing for the smelter is a key milestone that we achieved in 2Q23, and we are
now putting our focus and effort into the construction activities aiming for COD in 2025.”


PT Maruwai Coal
   •    ADMR’s production volume in 1H23 reached 2.54 million tonnes (Mt), a 66% increase
        over the period, with sales reaching 1.82 Mt, 42% higher than in 1H22. All production in
        the period came from PT Maruwai Coal, which produces hard coking coal with ultra-low
        ash, low phosphorus and high vitrinite content.
   •    Overburden removal reached 7.55 Mbcm in 1H23, 116% higher than in 1H22, leading to
        a 1H23 strip ratio of 2.97x, 30% increase from 1H22. The good performance from our
        contractor and supportive weather conditions drove the higher overburden removal
        volume in the period.
                                                       2Q23 vs.         2Q23 vs.                 1H23 vs.
                                 Units   2Q23    1Q23             2Q22             1H23    1H22
                                                        1Q23             2Q22                     1H22
Overburden Removal               Mbcm     4.25    3.30     29%     2.03    110%     7.55    3.50    116%
Production Volume                 Mt      1.32    1.22      8%     0.91     46%     2.54    1.53     66%
Sales Volume                      Mt      0.97    0.85     14%     0.69     40%     1.82    1.28     42%

   •    Japan remains the largest market for ADMR, but we are also encouraged by growth
        prospects in other regional markets. The chart below shows our sales destination by
        country in 1H23.


                         Korea
                          8%
             Indonesia
                10%                      Japan
                                          35%


           China
            20%



                                 India
                                  28%




                                                        1
Page 2
   •   We continue to invest into our facilities and infrastructure, with the upgrading of our hauling
       road making progress, while we also expand our fuel storage facility and staff
       accommodation camp in the Tuhup Port area.
   •   We have commenced the tender process to select our main contractor for the construction
       of the second barge loading conveyor at Tuhup Port. This expansion will increase our
       barge loading capacity, allowing us to take advantage of favorable weather conditions
       (water depth). Furthermore, we are tendering for contractors to expand our staff facilities
       in the Lampunut area to accommodate additional manpower, supporting our planned
       production increase to 6 Mtpa.


PT KALIMANTAN ALUMINIUM INDUSTRY (KAI)
   •   Through KAI, ADMR is actively developing opportunities in the mineral space, with a focus
       on downstream minerals processing. This business leads the Adaro Group’s
       transformation to support the green economy.
   •   In May 2023, KAI secured financing of $981.4 million and Rp1,547.9 billion for the
       development of a 500,000 tons per annum aluminum smelter, located in the industrial park
       being developed by PT Kalimantan Industrial Park Indonesia. In 2Q23, KAI completed the
       land preparation, earthworks, and construction of a temporary jetty and continues to work
       on the construction of other infrastructure related facilities.


HEALTH, SAFETY, AND ENVIRONMENT (HSE)
In 1H23, we experienced three lost-time injury (LTI) incidents and recorded a lost-time injury
frequency rate (LTIFR) of 0.55 and severity rate (SR) of 15.08 with total man-hours worked of
5,438,743 during the first six months of the year.


CORPORATE ACTIVITIES
Annual General Meeting of Shareholders
ADMR held its Annual General Meeting of Shareholders (AGMS) in Jakarta on 10 May 2023. The
AGMS discussed a total of five agendas which were, 1) approval of the company’s annual report
and ratification of the company’s consolidated financial statement for fiscal year 2022, 2) approval
for the appropriation of the company’s net income for fiscal year 2022, 3) approval for the
appointment of the public accounting firm to audit the company’s consolidated financial
statements for fiscal year 2023, 4) approval for the determination of the honorarium or salary and
other benefits for the members of the company’s Board of Commissioners and Board of Directors
for fiscal year 2023, and 5) report on the realization of the use of proceeds from ADMR’s public
offering.
                                                ###


                                                 2
Page 3
These materials have been prepared by PT Adaro Minerals Indonesia Tbk (the “Company”) and have not been
independently verified. No representation or warranty, expressed or implied, is made and no reliance should be placed
on the accuracy, fairness or completeness of the information presented or contained in these materials. The Company
or any of its affiliates, advisers or representatives accepts no liability whatsoever for any loss howsoever arising from
any information presented or contained in these materials. The information presented or contained in these materials
is subject to change without notice and its accuracy is not guaranteed.
These materials contain statements that constitute forward-looking statements. These statements include descriptions
regarding the intent, belief or current expectations of the Company or its officers with respect to the consolidated results
of operations and financial condition of the Company. These statements can be recognized by the use of words such
as “expects,” “plan,” “will,” “estimates,” “projects,” “intends,” or words of similar meaning. Such forward-looking
statements are not guarantees of future performance and involve risks and uncertainties, and actual results may differ
from those in the forward-looking statements as a result of various factors and assumptions. The Company has no
obligation and does not undertake to revise forward-looking statements to reflect future events or circumstances.
These materials are for information purposes only and do not constitute or form part of an offer, solicitation or invitation
of any offer to buy or subscribe for any securities of the Company, in any jurisdiction, nor should it or any part of it form
the basis of, or be relied upon in any connection with, any contract, commitment or investment decision whatsoever.
Any decision to purchase or subscribe for any securities of the Company should be made after seeking appropriate
professional advice.



For further information please contact:

Investors

Thomas Coombes | Thomas.Coombes@adaro.com

Media

Febriati Nadira | Febriati.Nadira@adaro.com




                                                             3

File

File Open PDF
Source IDX
Size0.17 MB
Published7 Aug 2023
Pages3
Characters7,295
Text sourceEmbedded text layer
OCR confidence—

Names mentioned 0 people and organisations named in the text · linked when the evidence is strong

The name pass has not read this document yet.

Extraction attempts how the parser did, and what it refused

Nothing structured was extracted from this document — the attempts below say why.

No extraction attempted yet.

↑↓ select ↵ open ⇧↵ see every result