Exploration Report – Quarter 3 2025
Introduction
During the period 1st of July to 30th of September 2025 (Q3 2025), PT Amman Mineral Nusa
Tenggara (PT AMNT), a subsidiary of PT Amman Mineral Internasional Tbk (PT AMI), carried out
exploration activities within IUPK Blocks II (Elang) and Block III (Rinti) located in Sumbawa,
Indonesia (Figure 1). There were no field exploration activities within Block I (Batu Hijau) and Blok
IV (Lampui).
Total exploration expenditure for Q3 2025 was approximately USD $ 2.69 M.
Figure 1. PT AMNT IUPK blocks, Sumbawa, Indonesia.
1
Page 2
Batu Hijau Block I
No exploration field work or costs incurred in Q3 2025.
Forward Plan:
• Review of previous exploration results.
2
Page 3
Elang Block II
Expenditure:
• Exploration activities included drilling and geological mapping. Costs were circa USD $
2.34 M.
Work Areas:
• Elang Cu-Au Project.
• Gerbang East Cu-Au Project.
• Sebu East Cu-Au Project.
• Elang waste dump plan area.
Exploration Parties:
• Manager - AMNT Exploration.
• Drilling contractor - PT Minera Nusa Drillindo (PT MND).
• Assay Laboratory (drill core, rock) - Intertek Utama Service (ITS).
Assessment Methods:
• Diamond drilling (3 rigs).
• Geological mapping and soil sampling.
• Alteration analyses using an ASD TerraSpec 4 Mineral Spectrometer.
Objectives:
• Resource development drilling continued at the Elang Cu-Au deposit (Figure 2). The
purpose of this infill program was to address data gaps, refine the geological model, and
enhance the confidence level of mineral resource classifications.
• Exploration drilling at Gerbang East is targeting the Cu-Au porphyry mineralisation
potential below a lithocap and diatreme breccias (Figure 2).
• Exploration drilling at Sebu East was conducted as a follow-up to the Q2 IP survey results
and previous drilling result.
• Geological mapping and grid soil sampling were conducted along the Sebu East IP survey
lines. The objective is to delineate the extent of the surficial Cu-Au geochemical
anomalies and to define new drill targets.
• Sterilisation drilling and geological mapping in the proposed Elang waste dump area were
carried out to ensure that no economically viable mineralisation is present beneath or
surrounding the planned dump site.
Exploration Results:
• Elang Cu-Au project diamond drilling (19 holes for 5,722.7 m):
o Resource infill, Elang - 10 holes (3,423.5 m) completed or in progress,
o Exploration drilling, Gerbang East - 6 holes (1,187.9 m) completed or in
progress,
o Exploration drilling, Sebu East - 1 hole (839.0 m) in progress,
o Sterilisation holes at Elang waste dump plan - 2 holes (272.3 m) completed or in
progress.
• Core samples submitted to the assay lab amounted to 1,841.
• Geological mapping program – 128 soil samples from Sebu East were submitted to the
lab.
1
Page 4
Forward Plan:
• Continue resource drilling at Elang, exploration drilling at Gerbang East, exploration
drilling at Sebu East and sterilisation drilling using 5 rigs.
Figure 2. Elang Block II Q3 2025 – Exploration Locations.
2
Page 5
Rinti Block III
Expenditure:
• Exploration activities included IP Survey data acquisition and geological mapping. Costs
were circa USD $ 351 K
Work Areas:
• Rinti Cu-Au Project.
Exploration Parties:
• Manager - AMNT Exploration.
• Geophysical survey contractor – PT Geoservices
Assessment Methods:
• IP (Induced Polarization) Survey - resistivity and chargeability.
• Geological mapping
Objective:
• The IP survey will investigate a lithocap system in the southern part of Rinti. This program
aims to identify the potential presence of an underlying Cu-Au porphyry system beneath
the lithocap and assist in determining the drilling targets (Figure 3).
• Detailed geological mapping was conducted at Rinti area with the objective of following
up on the IP geophysical survey results, particularly to identify surface geological
expressions corresponding to the IP anomalies.
Exploration Result:
• IP Survey acquisition – 8 lines (11.35 km) completed.
• Geological mapping program – 25 rock samples from Rinti were submitted to the lab.
Forward Plan:
• Exploration drilling (1 rig) at lithocap zone and high IP anomalies.
3
Page 6
Figure 3. Rinti Block III Q3 2025 – Exploration Locations.
4
Page 7
Lampui Block IV
No exploration field work or costs incurred in Q3 2025.
Forward Plan:
• Review of previous exploration results
5
Names mentioned 8 people and organisations named in the text · linked when the evidence is strong
unresolved
org
PT Amman Mineral Nusa Tenggara
p.1
unresolved
org
PT AMNT
p.1
unresolved
org
PT AMI
p.1
unresolved
org
PT AMNT IUPK
p.1
unresolved
org
PT Minera Nusa Drillindo
p.3
unresolved
org
PT MND
p.3
unresolved
org
PT Geoservices Assessment Methods
p.5