Page 1
Go To English Page
Nomor Surat 129/PGE500/2026-S0
Nama Perusahaan PT Pertamina Geothermal Energy Tbk
Kode Emiten PGEO
Lampiran 0
PGE-PLN IP Sepakati Tarif Listrik, Proyek PLTP Lahendong Bottoming Unit 15
Perihal
MW Siap Melangkah ke Tahap Berikutnya
Dengan ini kami untuk dan atas nama perusahaan menyampaikan Laporan Informasi atau Fakta Material sebagai
berikut:
Nama Emiten atau Perusahaan Publik PT Pertamina Geothermal Energy Tbk
Bidang Usaha Menyelenggarakan usaha bidang panas bumi dari hulu/hilir
Telepon +62 21 3983 3222
Faksimili +62 21 3983 3230
Alamat Surat Elektronik (email) datapge@pertamina.com
Tanggal Kejadian 14 April 2026
Jenis Informasi atau Fakta Material PGE-PLN IP Sepakati Tarif Listrik, Proyek PLTP Lahendong
Bottoming Unit 15 MW Siap Melangkah ke Tahap Berikutnya
Page 2
Uraian Informasi atau Fakta Material Konsorsium PT Pertamina Geothermal Energy Tbk (PGE)
(IDX: PGEO) dan PT PLN Indonesia Power (PLN IP)
mencapai kesepakatan tarif listrik dengan PT PLN (Persero)
untuk pengembangan proyek Pembangkit Listrik Tenaga
Panas Bumi (PLTP) Lahendong Bottoming Unit berkapasitas
15 megawatt (MW). Kesepakatan tersebut ditandai dengan
penandatanganan Berita Acara Kesepakatan Tarif yang
dilaksanakan di Bandung, Jawa Barat.
Penandatanganan ini menjadi bagian dari proses
pengembangan proyek sekaligus menegaskan komitmen para
pihak dalam mendorong pemanfaatan energi panas bumi
secara lebih optimal sebagai sumber energi bersih yang
berkelanjutan. Kesepakatan tarif yang dicapai juga merupakan
salah satu langkah penting dalam proses pengadaan
pembangkit melalui skema Independent Power Producer (IPP)
sebelum proyek memasuki tahap pengembangan selanjutnya.
Proyek PLTP Lahendong Bottoming Unit merupakan
pengembangan pembangkit yang memanfaatkan teknologi
binary (bottoming cycle). Teknologi ini mengolah panas sisa
dari operasi pembangkit panas bumi eksisting untuk
menghasilkan tambahan listrik. Melalui pendekatan tersebut,
bottoming cycle memungkinkan pemanfaatan sumber daya
panas bumi secara lebih optimal dengan menangkap energi
panas yang sebelumnya belum dimanfaatkan dalam proses
pembangkitan.
Direktur Utama PT Pertamina Geothermal Energy Tbk Ahmad
Yani menyampaikan bahwa capaian ini merupakan langkah
lanjutan PGE bersama PLN IP dalam mendukung percepatan
transisi energi nasional berbasis energi bersih.
Kami menyambut baik perkembangan proyek ini yang terus
berjalan sesuai rencana. Pemanfaatan teknologi bottoming
memungkinkan potensi energi panas bumi yang masih
tersedia dari operasi pembangkit eksisting dapat dimanfaatkan
secara lebih optimal. Melalui teknologi ini, panas sisa yang
sebelumnya belum termanfaatkan dapat dikonversi kembali
menjadi listrik, sehingga meningkatkan efisiensi pembangkitan
sekaligus memperkuat kontribusi panas bumi dalam bauran
energi bersih nasional. Ke depan, kami siap melanjutkan
proyek ini ke tahapan berikutnya agar manfaatnya dapat
segera dirasakan oleh masyarakat, ujarnya.
Setelah kesepakatan tarif tercapai, pengembangan proyek
akan dilanjutkan dengan sejumlah tahapan lanjutan. Tahapan
tersebut meliputi pembentukan joint venture, pelaksanaan
proses Engineering, Procurement, Construction, and
Commissioning (EPCC), hingga penyusunan Power Purchase
Agreement (PPA). Melalui tahapan tersebut, proyek ini
ditargetkan dapat mencapai Commercial Operation Date
(COD) pada tahun 2028.
Sebelumnya, pada akhir Desember 2025, PGE dan PLN IP
juga telah mencapai kesepakatan tarif listrik untuk proyek
PLTP Ulubelu Bottoming Unit berkapasitas 30 MW. Kedua
proyek ini merupakan bagian dari sinergi dua afiliasi BUMN di
bawah PT Pertamina (Persero) dan PT PLN (Persero)
tersebut, dalam pengembangan energi panas bumi di 19
proyek eksisting dengan total kapasitas sekitar 530 MW.
Sebagai pionir pengembangan energi panas bumi di Indonesia
Page 3
dengan pengalaman lebih dari empat dekade, PGE terus
memperluas pemanfaatan potensi panas bumi melalui
berbagai inovasi teknologi serta pengembangan proyek
strategis. Saat ini, PGE mengelola kapasitas terpasang
sebesar 727 MW dari enam wilayah operasi (own operation).
Selain itu, PGE turut mengembangkan sejumlah proyek untuk
mendukung peningkatan kapasitas terpasang dalam beberapa
tahun ke depan.
Dampak kejadian, informasi atau fakta
material tersebut terhadap kegiatan
operasional, hukum, kondisi keuangan,
atau kelangsungan usaha Emiten atau
Perusahaan Publik
Demikian untuk diketahui.
Hormat Kami,
PT Pertamina Geothermal Energy Tbk
Kitty Andhora
Corporate Secretary
PT Pertamina Geothermal Energy Tbk
Grha Pertamina - Tower Pertamax Lt.7
Telepon : +62 21 3983 3222, Fax : +62 21 3983 3230, https://www.pge.pertamina.
Nama Pengirim Kitty Andhora
Jabatan Corporate Secretary
Tanggal dan Waktu 14-04-2026 09:47
Dokumen ini merupakan dokumen resmi PT Pertamina Geothermal Energy Tbk yang tidak memerlukan tanda
tangan karena dihasilkan secara elektronik oleh sistem pelaporan elektronik. PT Pertamina Geothermal Energy Tbk
bertanggung jawab penuh atas informasi yang tertera didalam dokumen ini.
Page 4
Go To Indonesian Page
Letter / Announcement No. 129/PGE500/2026-S0
Issuer Name PT Pertamina Geothermal Energy Tbk
Issuer Code PGEO
Attachment 0
Subject PGE and PLN IP Agree on Electricity Rates; Lahendong Geothermal Power
Plant's 15 MW Bottoming Unit Project Ready to Move to the Next Phase
The company hereby announce the Material Information or Facts Report as follows
Name of Issuer or Public Company PT Pertamina Geothermal Energy Tbk
Business Activities Menyelenggarakan usaha bidang panas bumi dari hulu/hilir
Telephone +62 21 3983 3222
Faximile +62 21 3983 3230
Email Address datapge@pertamina.com
Date of Event 14 April 2026
PGE and PLN IP Agree on Electricity Rates; Lahendong
Type of Material Information or Facts Geothermal Power Plant's 15 MW Bottoming Unit Project
Ready to Move to the Next Phase
Page 5
Description of Material Information or A consortium comprising PT Pertamina Geothermal Energy
Facts Tbk (PGE) (IDX: PGEO) and PT PLN Indonesia Power (PLN
IP) has reached an electricity tariff agreement with PT PLN
(Persero) for the development of the 15-megawatt (MW)
Lahendong Bottoming Unit Geothermal Power Plant (PLTP)
project. The agreement was formalized with the signing of the
Tariff Agreement Minutes, which took place in Bandung, West
Java.
This signing is part of the projects development process and
reaffirms the parties commitment to promoting the more
optimal utilization of geothermal energy as a sustainable clean
energy source. The tariff agreement reached is also a crucial
step in the power plant procurement process through the
Independent Power Producer (IPP) scheme before the project
enters its next development phase.
The Lahendong Bottoming Unit Geothermal Power Plant
project involves the development of a power plant utilizing
binary (bottoming cycle) technology. This technology
processes waste heat from existing geothermal power plant
operations to generate additional electricity. Through this
approach, the bottoming cycle enables more optimal utilization
of geothermal resources by capturing thermal energy that was
previously unused in the power generation process.
Ahmad Yani, President Director of PT Pertamina Geothermal
Energy Tbk, stated that this achievement represents a further
step by PGE and PLN IP in supporting the acceleration of the
national clean energy transition.
We welcome the progress of this project, which continues to
proceed as planned. The use of bottoming technology allows
the remaining geothermal energy potential from existing power
plant operations to be utilized more optimally. Through this
technology, previously unused waste heat can be converted
back into electricity, thereby improving generation efficiency
while strengthening geothermal energys contribution to the
national clean energy mix. Moving forward, we are ready to
advance this project to the next phase so that its benefits can
be felt by the public as soon as possible, he said.
Once a tariff agreement is reached, project development will
proceed through several subsequent phases. These phases
include the formation of a joint venture, the execution of the
Engineering, Procurement, Construction, and Commissioning
(EPCC) process, and the drafting of a Power Purchase
Agreement (PPA). Through these phases, the project is
targeted to achieve Commercial Operation Date (COD) in
2028.
Previously, in late December 2025, PGE and PLN IP also
reached an agreement on electricity tariffs for the 30-MW
Ulubelu Bottoming Unit geothermal power plant project. These
two projects are part of the synergy between the two state-
owned enterprise affiliates under PT Pertamina (Persero) and
PT PLN (Persero) in the development of geothermal energy
across 19 existing projects with a total capacity of
approximately 530 MW.
As a pioneer in geothermal energy development in Indonesia
with over four decades of experience, PGE continues to
expand the utilization of geothermal potential through various
Page 6
technological innovations and the development of strategic
projects. Currently, PGE manages an installed capacity of 727
MW across six operational regions (own operations).
Additionally, PGE is developing several projects to support an
increase in installed capacity in the coming years.
Impact of event, material information or
facts towards Issuers or Public
Company’s operational activities, legal,
financial condition, or going concern
Thus to be informed accordingly.
Respectfully,
PT Pertamina Geothermal Energy Tbk
Kitty Andhora
Corporate Secretary
PT Pertamina Geothermal Energy Tbk
Grha Pertamina - Tower Pertamax Lt.7
Phone : +62 21 3983 3222, Fax : +62 21 3983 3230, https://www.pge.pertamina.com
Sender Name Kitty Andhora
Function Corporate Secretary
Date and Time 14-04-2026 09:47
This is an official document of PT Pertamina Geothermal Energy Tbk that does not require a signature as it was
generated electronically by the electronic reporting system. PT Pertamina Geothermal Energy Tbk is fully
responsible for the information contained within this document.
Names mentioned 6 people and organisations named in the text · linked when the evidence is strong
unresolved
org
PT PLN Indonesia Power
p.2 ×2
unresolved
org
PT PLN (Persero)
p.2 ×4
unresolved
person
Kitty Andhora
· Corporate Secretary
p.3 ×2
Extraction attempts how the parser did, and what it refused
Nothing structured was extracted from this document — the attempts below say why.
No extraction attempted yet.