 Jakarta, 25 Maret 2026
 No. 087/EMP.DIR/1070/03-26/E

 OTORITAS JASA KEUANGAN
 GEDUNG SOEMITRO DJOJOHADIKUSUMO
 JL. LAPANGAN BANTENG TIMUR NO. 2-4
 JAKARTA 10170

 U.P. : BAPAK HASAN FAWZI
        KEPALA EKSEKUTIF PENGAWAS INOVASI TEKNOLOGI SEKTOR KEUANGAN,
        ASET KEUANGAN DIGITAL, DAN ASET KRIPTO SEBAGAI PEJABAT SEMENTARA
        KEPALA EKSEKUTIF PENGAWAS PASAR MODAL, KEUANGAN DERIVATIF, DAN
        BURSA KARBON

 PT BURSA EFEK INDONESIA
 INDONESIA STOCK EXCHANGE BUILDING
 JL. JEND. SUDIRMAN KAV. 52-53
 JAKARTA 12190

 U.P. : JEFFREY HENDRIK
        PJS. DIREKTUR UTAMA

 PERIHAL :        KETERBUKAAN INFORMASI                RE. : INFORMATION DISCLOSURE


 Dengan Hormat,                                        Dear Sirs,

 Bersama ini kami informasikan bahwa PT Energi         We hereby inform that PT Energi Mega Persada
 Mega Persada Tbk (“Perseroan”) melalui anak           Tbk (the “Company”) through its subsidiary,
 usahanya, PT EMP Tunas Energi, telah berhasil         PT EMP Tunas Energi, had new oil discovery
 mendapatkan temuan minyak baru dari sumur             from the Cenako-1 Twin exploration well, which
 eksplorasi Cenako-1 Twin, yang merupakan              is part of the South CPP block in Riau,
 bagian dari blok South CPP di Riau, Sumatera.         Sumatera. The drilling activity of such
 Pengeboran sumur eksplorasi tersebut dilakukan        exploration well has currently reached 2,475
 hingga mencapai kedalaman 2.475 kaki (754             feet (754 meters) deep.
 meter).

 Berdasarkan data well testing dan subsurface          Based on the preliminary well testing result and
 awal tanggal 17 Maret 2026, struktur Cenako           the subsurface data on the 17th of March, 2026,
 diperkirakan memiliki kandungan minyak di             the Cenako structure has an estimated
 tempat (original oil in place) sekitar 15,6 juta      15.6 million barrels of Original Oil in Place.
 barel.

 Perseroan akan melanjutkan kegiatan eksplorasi        The Company will continue the exploration
 dan pengeboran lanjutan guna mengonversi              works and further drilling activities to convert
 temuan ini menjadi cadangan yang siap                 such discovery to become oil reserves for future
 dikembangkan      secara    komersial.    Kami        commercial development. We plan to acquire
 berencana untuk melakukan akuisisi data               the relevant seismic data and drill 3 additional
 seismik dan pengeboran di 3 sumur tambahan            wells with the potential production of around 500
 dengan potensi total produksi sebesar 500 barel       barrels of oil per day.
 minyak per hari.

 Perseroan akan berusaha untuk mempercepat             The Company will try to accelerate the
 konversi atas temuan tersebut menjadi produksi        conversion of this oil discovery to become
 komersial untuk menambah nilai bagi seluruh           commercial production so that it can add value

PT Energi Mega Persada Tbk   Bakrie Tower 32nd Floor         Jl. HR. Rasuna Said    p +62 21 2994 1500
                             Rasuna Epicentrum               Jakarta 12940          f +62 21 2994 1247
                                                             Indonesia
Page 2
pemangku kepentingan kami. Penemuan ini          to all of our respective stakeholders. The
merupakan bagian dari komitmen Perseroan         discovery is part of the Company’s commitment
dalam mendukung peningkatan cadangan             to the national’s hydrocarbon reserve increase
hidrokarbon   nasional    serta memperkuat       and the Country’s improved energy resilience.
ketahanan energi Indonesia.

Perseroan juga menyampaikan bahwa anak           The Company also reported that its subsidiary,
usahanya, EMP Bentu Limited, telah berhasil      EMP Bentu Limited, has successfully
mengaktifkan     kembali   lapangan    Bentu     reactivated the Bentu field, specifically, the
khususnya     di   sumur   Bentu-2,  melalui     Bentu-2 well through the pipeline construction
serangkaian pekerjaan pembangunan pipa           and the intensive workover activities. The
produksi dan perawatan sumur (workover) yang     Bentu-2 well was previously an idle well that was
cukup intensif. Sebelumnya, sumur Bentu-2        not in production. However, with the completion
merupakan sumur idle yang belum pernah           of the pipeline construction in December 2025,
diproduksikan. Namun dengan menyelesaikan        followed by the workover activities from
pekerjaan pembangunan pipa produksi di bulan     February to March 2026, the Company was able
Desember 2025, dilanjutkan dengan pekerjaan      to successfully reactivate and start the gas
workover di bulan Februari sampai dengan         production from the well. The investment spent
pertengahan Maret 2026, Perseroan kemudian       which led to such gas discovery has been kept
telah berhasil mengaktifkan kembali dan          below the approved budget, which reflects the
memproduksikan gas dari sumur tersebut.          Company’s efficient operations.
Investasi yang dikeluarkan untuk mendukung
penemuan gas ini tetap berada di bawah
anggaran, mencerminkan efisiensi Perseroan
dalam pelaksanaannya.

Hasil pengujian aliran gas menunjukkan bahwa     The initial gas flow test shows that Bentu-2 well
sumur Bentu-2 dapat memproduksikan gas           can produce around 5 million cubic feet gas per
sebesar 5 juta kaki kubik per hari dengan        day, with the total estimated production of
perkiraan total produksi dari lapangan Bentu     15 million cubic feet of gas per day from the
nantinya mencapai 15 juta kaki kubik per hari.   Bentu gas field. This achievement reflects the
Pencapaian ini mencerminkan upaya Perseroan      Company’s effort to contribute to the Country’s
untuk tetap berkontribusi dalam peningkatan      production increase.
produksi nasional.

Demikian hal ini kami sampaikan, dan apabila     Thus, we hereby convey this matter and should
ada informasi ataupun fakta material lainnya     there be any additional information or material
akan kami sampaikan kepada Otoritas Jasa         facts, we will submit it to the Financial Services
Keuangan dan Bursa Efek Indonesia.               Authority and the Indonesia Stock Exchange.

Atas perhatian Bapak kami ucapkan terima         Thank you for your attention.
kasih.


Hormat Kami,
PT ENERGI MEGA PERSADA Tbk




Syailendra S. Bakrie                        Edoardus Ardianto
Direktur Utama                              Wakil Direktur Utama

Tembusan Yth.:
- Deputi Komisioner Pengawas Pasar Modal II
- Direktur Penilaian Keuangan Perusahaan Sektor Riil



                                                                                                      2

File

File Open PDF
Source IDX
Size0.5 MB
Published25 Mar 2026
Pages2
Characters6,700
Text sourceEmbedded text layer
OCR confidence—

Names mentioned 13 people and organisations named in the text · linked when the evidence is strong

linked org Energi Mega Persada Tbk p.1 ×6
linked person Syailendra S. Bakrie p.2
linked person Edoardus Ardianto p.2
possible org OTORITAS JASA KEUANGAN p.1
possible person HASAN FAWZI p.1
possible org PT BURSA EFEK INDONESIA p.1 ×2
unresolved org HASAN FAWZI KEPALA EKSEKUTIF PENGAWAS INOVASI TEKNOLOGI p.1
unresolved org PT BURSA EFEK INDONESIA INDONESIA STOCK EXCHANGE BUILDING p.1
unresolved org INDONESIA STOCK EXCHANGE p.1 ×2
unresolved person PJS. · DIREKTUR UTAMA p.1
unresolved org PT EMP Tunas Energi p.1 ×2
unresolved org EMP Bentu Limited p.2 ×2

Extraction attempts how the parser did, and what it refused

Nothing structured was extracted from this document — the attempts below say why.

No extraction attempted yet.

Other files in this announcement 1

↑↓ select ↵ open ⇧↵ see every result