 Nomor Surat                           330/PGE500/2025-S0

 Nama Perusahaan                       PT Pertamina Geothermal Energy Tbk

 Kode Emiten                           PGEO

 Lampiran                              0
                                       PLTP Lumut Balai Unit 2 Beroperasi Penuh, PGE Tambah Kapasitas
 Perihal
                                       Terpasang 55 MW Menuju Target 1 GW


Dengan ini kami untuk dan atas nama perusahaan menyampaikan Laporan Informasi atau Fakta Material sebagai
berikut:

 Nama Emiten atau Perusahaan Publik            PT Pertamina Geothermal Energy Tbk

 Bidang Usaha                                  Menyelenggarakan usaha bidang panas bumi dari hulu/hilir



 Telepon                                       +62 21 3983 3222

 Faksimili                                     +62 21 3983 3230

 Alamat Surat Elektronik (email)               datapge@pertamina.com


 Tanggal Kejadian                              01 Juli 2025
 Jenis Informasi atau Fakta Material           PLTP Lumut Balai Unit 2 Beroperasi Penuh, PGE Tambah
                                               Kapasitas Terpasang 55 MW Menuju Target 1 GW
Page 2
Uraian Informasi atau Fakta Material    PT Pertamina Geothermal Energy Tbk (PGE) (IDX: PGEO)
                                        berhasil menyelesaikan tahapan penting dalam
                                        operasionalisasi Pembangkit Listrik Tenaga Panas Bumi
                                        (PLTP) Lumut Balai Unit 2 dengan kapasitas 55 megawatt
                                        (MW). Setelah melewati pengujian Unit Rated Capacity (URC)
                                        selama 72 jam berturut-turut dan dinyatakan layak operasi
                                        melalui penerbitan Surat Layak Operasi (SLO) pada 29 Juni
                                        2025, pembangkit ini kini beroperasi penuh dan menyalurkan
                                        listrik ke jaringan nasional. Dengan tambahan tersebut, PGE
                                        kini mengelola kapasitas terpasang sebesar 727,5 MW dari
                                        enam wilayah operasi.

                                        Proses pengujian URC yang berlangsung pada 26-29 Juni
                                        2025 menunjukkan performa pembangkitan yang stabil dan
                                        sesuai spesifikasi. Dengan selesainya penandatanganan
                                        Berita Acara URC dan penerbitan SLO, diharapkan proses
                                        integrasi dan sinkronisasi proyek dengan jaringan kelistrikan
                                        nasional dapat berjalan dengan lancar, serta memberikan
                                        kontribusi positif terhadap bauran energi nasional dari sumber
                                        energi baru terbarukan, khususnya dari panas bumi. Fase ini
                                        juga menjadi tonggak penting dalam monetisasi aset melalui
                                        transaksi penjualan listrik oleh PGE kepada PLN.

                                        Direktur Utama PT Pertamina Geothermal Energy Tbk (PGE)
                                        Julfi Hadi mengatakan bahwa capaian ini merupakan hasil
                                        kerja kolektif tim PGE di lapangan dan dukungan berbagai
                                        pemangku kepentingan. Kami bersyukur pembangkitan PLTP
                                        Lumut Balai Unit 2 kini dapat dimulai secara penuh dan
                                        konsisten. Ini adalah bagian dari komitmen jangka panjang
                                        PGE dalam menyediakan energi bersih berbasis panas bumi
                                        yang andal dan berkelanjutan. Dengan tambahan kapasitas
                                        ini, kami tidak hanya memperkuat bauran energi nasional,
                                        tetapi juga semakin mendekatkan langkah menuju target
                                        kapasitas terpasang yang dikelola mandiri sebesar 1 gigawatt
                                        (GW) pada 2-3 tahun mendatang, ujarnya.

                                        Julfi juga mengungkapkan bahwa langkah ini menjadi wujud
                                        nyata upaya PGE dalam berkontribusi mencapai target
                                        perluasan kapasitas pembangkit Energi Baru Terbarukan
                                        (EBT) hingga 76% dalam periode 2025-2034.

                                        Ke depannya, kami optimistis untuk terus mendukung
                                        percepatan target peningkatan kapasitas panas bumi nasional
                                        sebesar 5,2 GW pada periode tersebut, katanya.

                                        Selain PLTP Lumut Balai Unit 2, PGE juga tengah
                                        mengembangkan beberapa proyek strategis lainnya seperti
                                        PLTP Hululais Unit 1 & 2 (110 MW), serta sejumlah proyek co-
                                        generation berkapasitas total 230 MW. Baru-baru ini, pada 26
                                        Juni, PGE turut meresmikan eksplorasi (green field) PLTP
                                        Gunung Tiga yang terletak di Lampung dengan potensi
                                        kapasitas sebesar 55 MW.

Dampak kejadian, informasi atau fakta
material tersebut terhadap kegiatan
operasional, hukum, kondisi keuangan,
atau kelangsungan usaha Emiten atau
Perusahaan Publik



Demikian untuk diketahui.
Page 3
Hormat Kami,
PT Pertamina Geothermal Energy Tbk




Kitty Andhora

Corporate Secretary




PT Pertamina Geothermal Energy Tbk
Grha Pertamina - Tower Pertamax Lt.7
Telepon : +62 21 3983 3222, Fax : +62 21 3983 3230, https://www.pge.pertamina.



Nama Pengirim                     Kitty Andhora

Jabatan                           Corporate Secretary
Tanggal dan Waktu                 01-07-2025 22:57




   Dokumen ini merupakan dokumen resmi PT Pertamina Geothermal Energy Tbk yang tidak memerlukan tanda
tangan karena dihasilkan secara elektronik oleh sistem pelaporan elektronik. PT Pertamina Geothermal Energy Tbk
                   bertanggung jawab penuh atas informasi yang tertera didalam dokumen ini.
Page 4
Go To Indonesian Page

 Letter / Announcement No.           330/PGE500/2025-S0

 Issuer Name                         PT Pertamina Geothermal Energy Tbk

 Issuer Code                         PGEO

 Attachment                          0

 Subject                             PLTP Lumut Balai Unit 2 Fully Operational, PGE Adds 55 MW Installed
                                     Capacity Towards 1 GW Target

The company hereby announce the Material Information or Facts Report as follows

 Name of Issuer or Public Company            PT Pertamina Geothermal Energy Tbk

 Business Activities                         Menyelenggarakan usaha bidang panas bumi dari hulu/hilir


 Telephone                                   +62 21 3983 3222

 Faximile                                    +62 21 3983 3230

 Email Address                               datapge@pertamina.com


 Date of Event                               01 July 2025

                                             PLTP Lumut Balai Unit 2 Fully Operational, PGE Adds 55 MW
 Type of Material Information or Facts       Installed Capacity Towards 1 GW Target
Page 5
 Description of Material Information or     PT Pertamina Geothermal Energy Tbk (PGE) (IDX: PGEO)
 Facts                                      successfully completed an important stage in the
                                            operationalization of the 55 megawatt (MW) Lumut Balai Unit 2
                                            Geothermal Power Plant (PLTP). After passing the Unit Rated
                                            Capacity (URC) test for 72 consecutive hours and being
                                            declared fit for operation through the issuance of a Letter of
                                            Operation (SLO) on June 29, 2025, the plant is now fully
                                            operational and delivering electricity to the national grid. With
                                            this addition, PGE now manages an installed capacity of 727.5
                                            MW from six operating areas.

                                            The URC testing process, which took place from June 26-29,
                                            2025, demonstrated stable generation performance and
                                            compliance with specifications. With the completion of the
                                            signing of the URC Minutes and the issuance of the SLO, it is
                                            expected that the project integration and synchronization
                                            process with the national electricity network can run smoothly,
                                            and make a positive contribution to the national energy mix
                                            from new renewable energy sources, especially from
                                            geothermal. This phase is also an important milestone in asset
                                            monetization through electricity sales transactions by PGE to
                                            PLN.

                                            President Director of PT Pertamina Geothermal Energy Tbk
                                            (PGE) Julfi Hadi said that this achievement is the result of the
                                            collective work of the PGE team in the field and the support of
                                            various stakeholders. We are grateful that the Lumut Balai Unit
                                            2 geothermal power plant can now be fully and consistently
                                            commissioned. This is part of PGE's long-term commitment in
                                            providing reliable and sustainable geothermal-based clean
                                            energy. With this additional capacity, we are not only
                                            strengthening the national energy mix, but also moving closer
                                            to our target of 1 gigawatt (GW) of self-managed installed
                                            capacity in the next 2-3 years, he said.

                                            Julfi also revealed that this step is a tangible manifestation of
                                            PGE's efforts in contributing to achieving the target of
                                            expanding renewable energy generation capacity to 76% in
                                            the 2025-2034 period.

                                            Going forward, we are optimistic to continue supporting the
                                            acceleration of the national geothermal capacity increase
                                            target of 5.2 GW in that period, he said.

                                            In addition to the Lumut Balai Unit 2 geothermal plant, PGE is
                                            also developing several other strategic projects such as the
                                            Hululais Unit 1 & 2 geothermal plants (110 MW), as well as a
                                            number of co-generation projects with a total capacity of 230
                                            MW. Most recently, on June 26, PGE also inaugurated the
                                            exploration (green field) of the Gunung Tiga geothermal power
                                            plant located in Lampung with a potential capacity of 55 MW.

 Impact of event, material information or
 facts towards Issuers or Public
 Company’s operational activities, legal,
 financial condition, or going concern




Thus to be informed accordingly.


Respectfully,
Page 6
PT Pertamina Geothermal Energy Tbk




Kitty Andhora

Corporate Secretary




PT Pertamina Geothermal Energy Tbk
Grha Pertamina - Tower Pertamax Lt.7
Phone : +62 21 3983 3222, Fax : +62 21 3983 3230, https://www.pge.pertamina.com



Sender Name                        Kitty Andhora

Function                           Corporate Secretary

Date and Time                      01-07-2025 22:57




  This is an official document of PT Pertamina Geothermal Energy Tbk that does not require a signature as it was
     generated electronically by the electronic reporting system. PT Pertamina Geothermal Energy Tbk is fully
                           responsible for the information contained within this document.

File

File Open PDF
Source IDX
Size0.01 MB
Published1 Jul 2025
Pages6
Characters13,164
Text sourceEmbedded text layer
OCR confidence—

Names mentioned 3 people and organisations named in the text · linked when the evidence is strong

linked org Pertamina Geothermal Energy Tbk · Nama Perusahaan p.1 ×48
linked person Julfi Hadi p.2 ×2
unresolved person Kitty Andhora · Corporate Secretary p.3 ×2

Extraction attempts how the parser did, and what it refused

Nothing structured was extracted from this document — the attempts below say why.

No extraction attempted yet.

↑↓ select ↵ open ⇧↵ see every result