Barito Renewables to Increase Geothermal Asset Capacity by 53 MW
             with Salak Binary and Retrofit Projects

Jakarta, 31 May 2024 – PT Barito Renewables Tbk (BREN), through its subsidiary, Star Energy
Geothermal, is set to increase its total geothermal capacity by 116 MW across its three
operational areas in Salak, Darajat, and Wayang Windu. Of this, 53 MW will be achieved through
two strategic initiatives: the Salak Binary development and a Retrofit Program. This capacity
enhancement is part of BREN's growth strategy aimed at expanding through organic growth.

"This capacity addition is being undertaken through strategic measures, including efficiency
improvements in the units across the three operational areas via the retrofit project and the
Salak Binary development. The total capacity increase from the retrofit is expected to boost the
company's revenue by approximately US$ 40 million annually," said Hendra Tan, CEO of Barito
Renewables.

"The Salak Binary and retrofit projects are currently in progress, with completion targeted in
stages until 2026. This reflects our commitment to continuously develop our business and
support the Indonesian Government's energy transition target," Hendra Tan added.

Explaining the Salak Binary project, Suharsono Darmono, Deputy Chief of Asset Management
at Star Energy Geothermal, stated, "Salak Binary is an innovative application of the latest
geothermal technology that converts heat energy from hot brine water, previously unused, into
electricity.”

"The retrofit project is part of our efforts to enhance the efficiency of our power plants.
Efficiencies undertaken by Star Energy Geothermal include re-engineering, improvements, and
optimization, such as replacing cooling towers and turbine rotors with newer technology,"
Suharsono added.

In addition to the Salak Binary project, Star Energy Geothermal’s retrofit project will add 39.2
MW of capacity across the Salak, Darajat, and Wayang Windu operational areas. The
Commercial Operation Date (COD) for Salak and Wayang Windu is scheduled for 2025, while
Darajat is expected to be completed in 2026.



                                             ---- END ----
Page 2
About Barito Renewables:

Barito Renewables (IDX: BREN) is a leading renewable energy company in Indonesia and the renewable
energy unit of Barito Pacific Group, committed to providing clean and sustainable energy solutions.
With a strong focus on environmental responsibility and community engagement in its operational
areas, BREN plays a crucial role in Indonesia's transition to a greener and more sustainable energy
landscape. BREN's subsidiary, Star Energy Geothermal, currently operates geothermal power plants
with a total capacity of 886 MW. Through Barito Wind, the company also owns the Sidrap wind power
plant in South Sulawesi with a capacity of 75 MW. Visit the company’s website at:
https://baritorenewables.co.id.

For more information, please contact: corpsec@baritorenewables.co.id

File

File Open PDF
Source IDX
Size0.08 MB
Published31 May 2024
Pages2
Characters3,081
Text sourceEmbedded text layer
OCR confidence—

Names mentioned 2 people and organisations named in the text · linked when the evidence is strong

possible org Barito Pacific p.2
unresolved org Barito Renewables Tbk p.1 ×2

Extraction attempts how the parser did, and what it refused

Nothing structured was extracted from this document — the attempts below say why.

No extraction attempted yet.

↑↓ select ↵ open ⇧↵ see every result