2024     LAPORAN
   PT. TRUBA BARA BANYUEKSPLORASI
                        ENIM

               PERIODE JANUARI – MARET 2024




                   BENAKAT BLOCK




                                            PINANG BLOCK



         KECAMATAN GUNUNG MEGANG, KABUPATEN MUARA
               PIT 3A – LEKUKAM BLOCK

                                        ENIM
                         PROVINSI SUMATERA SELATAN
                                                           LEKUKAM BLOCK




                                           LAPORAN TAHUNAN
    KEGIATAN EKSPLORASI
         PERIODE TAHUN 2022




                 PT. TRUBA BARA BANYU ENIM (PT. TBBE)
   KECAMATAN BENAKAT AND GUNUNG MEGANG, KABUPATEN MUARA ENIM,
                         PROVINSI SUMATERA SELATAN


                                   DILAPORKAN OLEH,
          DEPARTEMEN EKSPLORASI, GEOLOGI, GEOTEKNIKAL DAN
                                 COAL QUALITY (EG2C)
                           1
Page 2
                                 PT. TRUBA BARA BANYU ENIM


                                                           DAFTAR ISI


DAFTAR ISI ........................................................................................................................................ 2
KATA PENGANTAR ............................................................................................................................ 3
1. AKTIVITAS KEGIATAN EKSPLORASI ........................................................................................... 4
1.1. Wilayah Pemboran Eksplorasi .............................................................................................. 4
1.2.       Metoda Pemboran Eksplorasi .............................................................................................. 5
1.3.       Rencana dan Realisasi Pemboran Eksplorasi ....................................................................... 7
1.4.       Pengawasan Pemboran Eksplorasi ....................................................................................... 7
1.5.       Rencana Eksplorasi Selanjutnya ........................................................................................... 7




                                                                      2
Page 3
                       PT. TRUBA BARA BANYU ENIM


                                         KATA PENGANTAR


PT. RMK ENERGY TBK (PT. RMKE) adalah induk perusahaan pertambangan batubara yang melakukan
kegiatan eksplorasi dan kegiatan penambangan yang terletak di daerah Gunung Megang, Kabupaten
Muara Enim, Provinsi Sumatera Selatan.

PT. RMK ENERGY TBK (PT. RMKE) memiliki anak perusahaan yang bergerak dibidang pertambangan,
yaitu: PT. TRUBA BARA BANYU ENIM (PT. TBBE).

Wilayah Eksplorasi PT. TRUBA BARA BANYU ENIM (PT. TBBE) adalah 10.242 Ha yang merupakan
anak perusahaan dari PT. RMK ENERGY TBK (PT. RMKE) di bagi atas tiga (3) Blok Eksplorasi dimana
bagian Timur adalah Blok Lekukam untuk area 3.720 Ha, bagian Tengah adalah Blok Pinang untuk
area 2000 Ha dan bagian Barat adalah Blok Benakat untuk area 4.522 Ha.

Dalam rangka memenuhi ketentuan III.1.6 perubahan peraturan nomor 1-E Tentang kewajiban
penyampaian informasi, lampiran keputusan direksi PT. BURSA EFEK INDONESIA No kep-
00015/BEI/01-2021, maka dengan ini kami sampaikan laporan Tri wulan eksplorasi Tahunan 2023
PT. TRUBA BARA BANYU ENIM (PT. TBBE).




                                               3
Page 4
                             PT. TRUBA BARA BANYU ENIM

                                       1. AKTIVITAS KEGIATAN EKSPLORASI


1.1. Wilayah Pemboran Eksplorasi


Wilayah Eksplorasi PT. Truba Bara Banyu Enim (PT. TBBE) adalah 10.242 Ha yang merupakan anak
perusahaan dari PT. RMK ENERGY TBK (PT. RMKE) di bagi atas tiga (3) Blok Eksplorasi yakni bagian
Timur adalah Blok Lekukam untuk area 3.720 Ha, bagian Tengah adalah Blok Pinang untuk area 2000
Ha dan bagian Barat adalah Blok Benakat (4.522 Ha) terlampir pada gambar 1.1.
Kegiatan eksplorasi yang dilakukan PT. Truba Bara Banyu Enim (PT. TBBE) di Periode Januari hingga
Maret tahun 2024 adalah kegiatan pemboran Eksplorasi untuk menentukan geometri batubara di
area PIT 3 di Desa Gunung Megang Dalam dan Desa Gunung Megang Luar di Kecamatan Gunung
Megang, Kabupaten Muara Enim, Provinsi Sumatera Selatan. Kegiatan Eksplorasi pada area Blok
Pinang saat ini masih dalam proses sosialisasi kepada warga sekitar terutama pada pemilik lahan
yang bersingungngan dengan rencana titik bor dan akses eksplorasi. Block Benakat hingga saat ini
belum terdapat rencana kegiatan eksplorasi.




                            BENAKAT BLOCK



                                                            PINANG BLOCK




                                                                                     LEKUKAM BLOCK




Gambar 1.1. Blok Lekukam dilakukan Pemboran Eksplorasi di PIT 3 di Konsesi PT.Truba Bara Banyu Enim (PT. TBBE)




                                                           4
Page 5
                                  PT. TRUBA BARA BANYU ENIM

1.2. Metoda Pemboran Eksplorasi


Pemboran Eksplorasi periode Januari - Maret 2024 yang dilakukan di Blok Lekukam bertujuan untuk
mengetahui kemenurusan dan kepastian akan nilai cadangan pada Pit 3, Sebanyak 4 titik pemboran
telah diselesaikan pada durasi Jan – Mar 2024 ini, dengan total kedalaman 485.50 meter, Total
Coring sebesar 433.79 meter, serta Total Non Coring sebesar 51.71 meter, dengan jumlah sample
batubara yang telah dilakukan analisa sebanyak 39 sample, detail dari data hasil pemboran dapat
dilihat pada tabel 1.1 dan dapat dilihat di gambar 1.1 untuk detail lokasi pemboran.
Tabel 1.1 Drill Hole Summary

                                                                DRILLHOLES SUMMARY JAN - MAR 2024
                                                                                       Drilling (meter)
                                                 Koordinat                                                              Recoverry
 No           TIME            Hole ID                                    OPEN HOLE       FULL CORING      TOTAL DEPTH                Rig Jacro   Estimasi Biaya
                                          X             Y        Z           (m)              (m)             (m)          (%)
  1 24 Jan - 3 Feb 2024    TBBE24_039 375905.764 9617388.244    24.783                        96.5           96.5            82% J200-01         Rp109,258,698
  2 19 Feb - 27 Feb 2024 TBBE24_040 375930.831 9616882.666      30.137                        119             119            66% J200-01         Rp134,733,524
  3 1 Mar - 12 Mar 2024 TBBE24_041 375785.868 9616620.306       32.486       6.21           121.79            128            94% J200-01         Rp144,923,454
  4 19 Mar - 27 Mar 2024 TBBE24_042 375569.225 961599.950       32.838       45.5             96.5            142           100% J200-01         Rp160,774,457
                                        TOTAL REALISASI KEDALAMAN                                            485.5                               Rp549,690,133
    - Total Sample Batubara : 39 Sample


Gambar 1.1 Kegiatan Pemboran Eksplorasi di PIT 3 Lekukam di Konsesi PT. TBBE




                                                         PIT 3A




                                                                       5
Page 6
                     PT. TRUBA BARA BANYU ENIM
Gambar 1.2 Aktivitas Pemboran Eksplorasi di PIT 3 Lekukam di Konsesi PT. TBBE




                                            6
Page 7
                       PT. TRUBA BARA BANYU ENIM




1.3. Rencana dan Realisasi Pemboran Eksplorasi

Blok Lekukam khususnya PIT 3A untuk rencana ada 6 titik lubang bor eksplorasi dan quality dengan
metoda full coring ukuran NQ yang bertujuan untuk mengetahui litologi dan data quality batubara
yang telah terealisasi 4 titik lubang bor di triwulan Januari hingga Maret 2024 dengan menggunakan
satu (1) unit Bor Jacro 175 yang dapat dilihat pada tabel 1.3.
Tabel 1.3 Rencana dan Realisasi Pemboran Eksplorasi di PIT 3A

     dh_name            X             Y              Z                     Status

    TBBE24_038     375904.385    9616888.72         25.02           Terealisasi (Jan 2024)
    TBBE24_039     375840.999    9616752.771        22.5         Terealisasi (Jan - Feb 2024)
    TBBE24_040     375777.613    9616616.821        32.3            Terealisasi (Feb 2024)
    TBBE24_025     375620.209    9616752.513        20.78             Belum Terealisasi
    TBBE24_026     375556.823    9616616.563        32.65        Terealisasi (Feb - Mar 2024)
    TBBE24_027     375493.438    9616480.614        34.09             Belum Terealisasi


1.4. Pengawasan Pemboran Eksplorasi

Kegiatan pemboran Eksplorasi triwulan Jan – Mar 2024 di area PIT 3 di Blok Lekukam dibawah
pengawasan Geologist kompeten PT. Truba Bara Banyu Enim (PT. TBBE) dengan menggunakan unit
bor Jacro 175.


1.5. Rencana Eksplorasi 2024
    Periode 2024 rencannya akan dilakukan kegiatan eksplorasi pada area Blok Leukukam dan Block
    Pinang dengan detail kegiatan tertera pada table di bawah ini.




                                                7
Page 8
                       PT. TRUBA BARA BANYU ENIM

                                                 Kegiatan          Kuantitas
                               EKSPLORASI
                               1. Pemetaan
                                   - Geology
                                   - Topografi

                               2. Pemboran
                                   - Open Hole                  14,386.03 meter
                                   - Coring                      3,633.01 meter

                               3. Geofisika Logging (Sewa)             10 Bulan
                               4. Analisis Kualitas                2,160 sample
                               5. Analisis Geotek                  1,344 sample


Rencana kegiatan eksplorasi mulai dari Januari 2024, tahap awal dari kegiatan ini adalah sosialisasi
terhadap pemilik lahan yang area nya dilewati oleh recana titik bor. 3x Jacro 200 menjadi opsi dalam
kegiatan eksplorasi ini, Penambahan jumlah mesin pengeboran masih sangat terbuka melihat dari
durasi waktu yang tersedia nanti nya setelah seluruh recanan titik bor diberikan izin kegiatan
eksplorasi oleh pemilik lahan yang terdampak.

Pengeboran akan dilakukan secara bertahap, dari kegiatan pengeboran stratigraphy, untuk
memastikan susunan lapisan batubara, melihat kondisi geologi lokal di IUP PT. TBBE yang masuk
kedalam Kondisi geology Sederhana, maka tahap eksplorasi Tereka dilakukan pengeboran dengan
jarak antar line pengeboran sejauh 1000m, sedangkan tahap eksplorasi Tertunjuk akan dilakukan
pengeboran dengan jarak antar line pengeboran sejauh 500m, untuk tahap eksplorasi Terukur akan
dilakukan dengan jarak antar line pengebroan sejauh 250m.

Gambar 1.5. Rencana Pemboran Eksplorasi Lanjut 2024




                                                    8
Page 9
                PT. TRUBA BARA BANYU ENIM


              Rencana Pemboran Explorasi Lanjutan TW II_April_Juni 2024


        DESCRIPTION            24-Apr             24-May              24-Jun
       HOLES               17 Holes           18 Holes            17 Holes
       DAYS                30 Days            31 Days             30 Days
       TOTAL DEPTH         1,800 meter        1,860 meter         1,800 meter
       CORING              363 meter          375 meter           363 meter
       NON CORING          1,437 meter        1,485 meter         1,437 meter
       QUALITY             216 Ply            223 Ply             216 Ply
       GEOTEK              134 sample         139 sample          134 sample


                 Estimasi Biaya Explorasi Lanjutan TWII_April_Juni 2024
  DESCRIPTION        HARGA SATUAN             24-Apr         24-May           24-Jun
CORING              Rp580,000.00         Rp210,513,039   Rp217,530,140   Rp210,513,039
NON CORING          Rp460,000.00         Rp661,124,432   Rp683,161,913   Rp661,124,432
GEOFISIKA LOGGING Rp120,000,000.00       Rp120,000,000   Rp120,000,000   Rp120,000,000
QUALITY             Rp1,503,455.00       Rp324,435,671   Rp335,250,194   Rp324,435,671
GEOTEK              Rp1,080,000.00       Rp145,013,167   Rp149,846,939   Rp145,013,167
               TOTAL                      Rp1,461,086,308 Rp1,505,789,185 Rp1,461,086,308




                                         9

File

File Open PDF
Source IDX
Size1.75 MB
Published16 Apr 2024
Pages9
Characters12,431
Text sourceEmbedded text layer
OCR confidence—

Names mentioned 12 people and organisations named in the text · linked when the evidence is strong

linked org RMK ENERGY TBK p.3 ×11
possible org BURSA EFEK INDONESIA p.3
unresolved org PT. TRUBA BARA BANYUEKSPLORASI ENIM p.1
unresolved org PT. TRUBA BARA BANYU ENIM p.1 ×10
unresolved org PT. TBBE p.1 ×10
unresolved org PT. TRUBA BARA BANYU ENIM DAFTAR ISI DAFTAR p.2
unresolved org PT. TRUBA BARA BANYU ENIM KATA PENGANTAR p.3
unresolved org PT. RMKE p.3 ×4
unresolved org PT. TBBE PIT p.5
unresolved org PT. TRUBA BARA BANYU ENIM Gambar p.6
unresolved org PT. TRUBA BARA BANYU ENIM Kegiatan p.8
unresolved org PT. TRUBA BARA BANYU ENIM Rencana Pemboran Explorasi p.9

Extraction attempts how the parser did, and what it refused

Nothing structured was extracted from this document — the attempts below say why.

No extraction attempted yet.

Other files in this announcement 1

↑↓ select ↵ open ⇧↵ see every result