B. Operasional dan Kondisi Terkini Perseroan (Disampaikan kepada Publik)
Current Operations and Condition of the Company (Disclosed to the Public)
1. Kondisi operasional terkini Perseroan dan masing-masing entitas anak Perseroan
The current operational condition of the Company and each of its subsidiaries
Jawaban / Answer:
Kondisi operasional perseroan dan entitas anak berjalan dengan baik dengan
fokus pada strategi Transformasi, Efisirnsi, Digitalisasi dan Manajemen Resiko.
The operational condition of the Company and its subsidiaries is performing well,
with a focus on the strategies of Transformation, Efficiency, Digitalization, and Risk
Management.
2. Fokus strategi usaha yang saat ini sedang dilakukan Perseroan
The current business strategy focus being implemented by the Company
Jawaban / Answer:
Pengembangan CNG Station dan meningkatkan penjualan
Development of CNG Stations and increasing sales
3. Strategi pengembangan ke depan yang akan dilakukan Perseroan
The Company's future development strategies
Jawaban / Answer:
Pengembangan pasar retail dan perluasan area distribusi melalui pembangunan
CNG Station dan pembangunan LNG
Development of the retail market and expansion of distribution areas through the
construction of CNG Stations and LNG facilities
4. Kendala yang dihadapi Perseroan dalam merealisasikan strategi Perseroan yang
telah direncanakan sebelumnya
Challenges faced by the Company in realizing its previously planned strategies
Jawaban / Answer:
Kendala yg dihadapi perseroan terkait dengan regulasi dan aturan yg berkaitan
dengan proses- proses yg melibatkan antar instansi pemerintah, kompetisi harga
jual yg ketat, belum optimalnya penetrasi pasar retail dan portofolio produk
sebagai target peningkatan revenue perseroan.
The challenges faced by the Company are related to regulations and rules
involving processes between government agencies, intense price competition,
suboptimal retail market penetration, and product portfolio as targets for
increasing the Company's revenue.
Page 2
C. Penggunaan Dana Hasil Penawaran Umum dan Kondisi Keuangan Terkini
(Disampaikan kepada Publik)
Use of Proceeds from the Public Offering and Current Financial Condition (Disclosed
to the Public)
1. Sehubungan dengan sisa dana hasil penawaran umum Perseroan per 30 Juni dan 31
Desember 2024 yang belum digunakan sebesar Rp100,55 miliar, agar dijelaskan:
In relation to the remaining proceeds from the Company’s public offering as of June 30 and
December 31, 2024, amounting to IDR 100.55 billion, please provide an explanation
regarding the following:
a. Latar belakang dan penyebab Perseroan belum menggunakan sisa dana hasil
penawaran umum tersebut.
The background and reasons why the Company has not utilized the remaining
proceeds from the public offering.
Jawaban:
Dikarenakan alokasi LNG masih dalam proses sehingga perseroan belum
merealisasikan pembelian peralatan untuk peralatan LNG tersebut.
Answer:
As the LNG allocation is still in progress, the Company has not yet realized the
purchase of equipment related to the LNG infrastructure.
b. Kondisi terkini atas sisa dana hasil penawaran umum tersebut.
The current status of the remaining proceeds from the public offering.
Jawaban:
Sisa dana hasil penawaran umum berada pada rekening perseroan.
Answer:
The remaining proceeds from the public offering are currently held in the Company’s
bank account.
c. Informasi mengenai pemindahan penempatan sisa dana hasil penawaran umum sejak
per 30 Juni sampai dengan 31 Desember 2024.
Information on any transfers or reallocations of the remaining public offering proceeds
from June 30 to December 31, 2024.
Jawaban:
Dana awal hasil penawaran umum berada di Bank Negara Indonesia rekening
perseroan untuk selanjutnya sisa dana hasil penawaran umum berada di rekening
perseroan sesuai dengan Laporan Penggunaan Dana per 31 Desember 2024.
Penempatan Dana berada di Bank Muamalat, Bank Pembangunan Daerah Jawa Barat
dan Banten Syariah, Bank Mandiri, Bank Negara Indonesia, Bank Rakyat Indonesia,
Bank Central Asia, Bank Pembangunan Daerah Jawa Barat dan Banten.
Page 3
Answer:
The initial proceeds from the public offering were placed in the Company’s account at
Bank Negara Indonesia. Subsequently, the remaining proceeds have been held in the
Company’s accounts as disclosed in the Fund Utilization Report as of December 31,
2024. The funds are placed in Bank Muamalat, Bank Pembangunan Daerah Jawa
Barat dan Banten Syariah, Bank Mandiri, Bank Negara Indonesia, Bank Rakyat
Indonesia, Bank Central Asia, and Bank Pembangunan Daerah Jawa Barat dan
Banten.
2. Informasi mengenai rencana periode waktu atas realisasi penggunaan dana penawaran
umum tersebut.
Information regarding the planned timeframe for the realization of the use of these public
offering proceeds.
Jawaban:
Realisasi penggunaan dana penawaran umum diproyeksikan akan terserap secara
keseluruhan pada kuartal I tahun 2027.
Answer:
The realization of the use of public offering proceeds is projected to be fully absorbed by
the first quarter of 2027.
a. Dampak dan konsekuensi bagi Perseroan atas belum digunakannya sisa dana
penawaran umum tersebut terhadap kegiatan operasi dan kondisi keuangan Perseroan.
The impact and consequences for the Company due to the unutilized portion of the public
offering proceeds on its operational activities and financial condition.
Jawaban:
Peningkatan saldo kas yang ditempatkan di produk bank yang aman.
Answer:
An increase in cash balances, which have been placed in secure banking products.
b. Latar belakang dan penyebab tidak ada perubahan penggunaan dana selama bulan Juli
sampai Desember 2024.
The background and reasons for no changes in the use of proceeds during the period
from July to December 2024.
Jawaban:
Dikarenakan belum adanya realisasi pembangunan stasiun LNG.
Answer:
Because there has been no realization yet of the LNG station construction.
Page 4
c. Rencana Perseroan untuk melakukan perubahan penggunaan dana (jika ada).
The Company’s plans to change the use of proceeds (if any).
Jawaban:
Belum ada rencana perubahan penggunaan dana.
Answer:
There are currently no plans to change the use of proceeds.
2. Sehubungan dengan penggunaan dana untuk pembangunan stasiun LNG, agar
dijelaskan:
In relation to the use of funds for the construction of the LNG station, please provide
the following details:
a. Perkembangan terkini atas proses pembangunan stasiun LNG.
The latest development in the LNG station construction process.
Jawaban:
Dalam proses detail engineering design
Answer:
Currently in the detailed engineering design process.
b. Dokumentasi foto terkini atas proses pembangunan stasiun LNG.
Recent photo documentation of the LNG station construction process.
Jawaban:
Answer :
Page 5
c. Perkembangan terkini atas proses perolehan alokasi gas.
The latest update on the process of obtaining gas allocation.
Jawaban:
Dalam proses penetapan alokasi gas bumi oleh SKK MIGAS berdasarkan notulen rapat
yang dihadiri oleh perwakilan PT Pertamina EP, PT Citra Nusantara Gemilang Tbk dan PT
Citra Nusantara Gemilang Tbk tanggal 28 Februari 2025.
Answer:
The natural gas allocation is currently in the determination process by SKK MIGAS, based
on the minutes of a meeting attended by representatives of PT Pertamina EP, PT Citra
Nusantara Gemilang Tbk, and PT Citra Nusantara Gemilang Tbk on February 28, 2025.
d. Kendala yang dihadapi Perseroan dalam melakukan realisasi penggunaan dana untuk
pembangunan stasiun LNG.
The obstacles faced by the Company in realizing the use of funds for the construction of
the LNG station.
Jawaban:
Belum dimulainya pembangunan di LNG Station Galian dikarenakan menunggu terbitnya
surat alokasi gas dari Kementerian Energi dan Sumber Daya Mineral.
Answer:
The construction at the LNG Station Galian has not commenced due to the pending
issuance of the gas allocation letter from the Ministry of Energy and Mineral Resources.
e. Sehubungan dengan rencana penggunaan dana untuk pembangunan stasiun LNG agar
disampaikan informasi mengenai rincian penggunaan dana tersebut mengisi tabel
berikut:
In relation to the planned use of funds for the construction of the LNG station, please
provide details of the fund allocation in the following table:
Bentuk Skema
No. Nilai Pihak/Pemasok
Jasa/Pekerjaan Pembayaran
Pekerjaan LNG liquefaction Rp
1. Plant 1,5 MMSCFD 131.500.000.000
Tempo PT GT Ladang Teknik
f. Informasi mengenai akun dalam laporan keuangan auditan yang merefleksikan
penggunaan dana untuk pembangunan stasiun LNG beserta saldonya per 31 Desember
2024.
Information regarding the accounts in the audited financial statements that reflect the use
of funds for the LNG station construction along with the balances as of December 31, 2024.
Page 6
Jawaban:
Pertanggungjawaban atas pembayaran uang muka operasional perseroan dilakukan pada
saat CNG Station Grobogan sudah beroperasi.
Answer:
The accountability for the payment of operational advances by the Company will be
recognized once the Grobogan CNG Station becomes operational.
g. Sehubungan dengan realisasi penggunaan dana untuk pembangunan stasiun LNG
sebesar Rp55,39 miliar agar disampaikan informasi mengenai rincian nama pihak yang
menerima pembayaran atas dana tersebut dengan mengisi tabel berikut:
In relation to the realization of fund utilization for the construction of the LNG station
amounting to IDR 55.39 billion, please provide details of the recipients of the payments by
completing the following table:
h. Dalam hal pembayaran dana tersebut dibayarkan melalui mekanisme pembayaran uang
muka, agar disampaikan informasi mengenai tanggal pembayaran, realisasi dan
perjanjian yang mendasari atas pembayaran tersebut dengan mengisi tabel berikut:
In the event that the fund disbursement was made through an advance payment
mechanism, please provide information regarding the payment date, realization, and the
underlying agreement of the payment by completing the following table:
i. Informasi mengenai tindak lanjut Perseroan atas penawaran dari beberapa perusahaan
untuk pelaksanaan proyek antara lain PT GT Ladang Teknik dan PT Galileo
Technologies.
Information regarding the Company’s follow-up on proposals from several companies for
the project implementation, including PT GT Ladang Teknik and PT Galileo Technologies.
Page 7
Jawaban:
Perseroan mengeluarkan surat pesanan kepada PT GT Ladang Teknik dengan nomor
surat CNG/PO/24/0149.
Answer :
The Company issued a purchase order to PT GT Ladang Teknik with reference number
CNG/PO/24/0149.
j. Informasi mengenai pihak pemenang tender atas pihak vendor yang akan melakukan
pembangunan stasiun LNG sekurang-kurangnya terkait:
Information regarding the tender winner/vendor appointed to construct the LNG station,
covering at minimum:
1) Nama dan alamat vendor:
Name and address of the vendor:
PT. GT Ladang Teknik
Alamanda Tower 22nd floor
Jl. TB Simatupang Kav 23 – 24
Jakarta Selatan 12430
2) Nama manajemen dan individu perwakilan vendor:
Name of the management and individual representative of the vendor:
Uran Tumborang selaku direktur
Uran Tumborang as Director
3) Pengalaman dan portofolio vendor:
Vendor's experience and portfolio:
a. Pembangunan terminal LNG di Teluk Lamong – Jawa Timur
b. Regasification Plant (Main Equipment) & LNG Filling Station Terminal LNG Jawa
Timur
c. Pembangunan LNG Liquefaction Plant Pasuruan – Jawa Timur
d. Pembangunan LNG Infrastructure for Gas PP di Nias
4) Skema pembayaran kepada vendor
Payment scheme to the vendor:
o Term I : 50% DP
o Term II : 25% setelah progress DED mencapai 50%
o Term III : 25% setelah progress DED mencapai 100%
5) Jangka waktu kerja sama Perseroan dengan vendor:
Duration of the cooperation between the Company and the vendor:
18 (delapan belas) bulan sejak tanggal surat pesanan dibuat atau tanggal 6 Maret
2024
Eighteen (18) months from the date of the purchase order issuance, i.e., March 6,
2024
6) Latar belakang dan alasan pemilihan vendor tersebut:
Background and reason for selecting the vendor:
Vendor tersebut pernah melakukan pekerjaan EPC project-project yang
berhubungan dengan LNG di Indonesia.
The vendor has previously undertaken EPC projects related to LNG in Indonesia.
Page 8
7) Ruang lingkup pekerjaan yang dikerjakan oleh vendor:
Scope of work to be carried out by the vendor:
1) Pekerjaan DED (Detail Engineering Design)
2) Pekerjaan EPC
3) Detail Engineering Design (DED)
4) EPC (Engineering, Procurement, and Construction) work
8) Informasi singkat mengenai profil vendor:
Brief information about the vendor’s profile:
Jawaban :
Vendor tersebut pernah melakukan pekerjaan EPC project-project yang
berhubungan dengan LNG di Indonesia.
Answer :
The vendor has prior experience executing EPC projects related to LNG in Indonesia.
k. Perseroan agar menyampaikan seluruh salinan kontrak atau perjanjian dengan vendor
dan Perseroan yang memuat informasi sekurang-kurangnya
The Company shall submit all copies of contracts or agreements with the vendor
containing at least the following information:
1) Detail pekerjaan;
Scope of work:
• Pekerjaan DED (Detail Engineering Design)
• Pekerjaan EPC
• Detail Engineering Design (DED)
• EPC (Engineering, Procurement, and Construction) work
2) Timeline atau lini masa tanggal mulai dan jangka waktu serta kapan selesai;
Timeline including start date, duration, and expected completion date:
12 – 14 bulan setelah uang muka
12 – 14 months after down payment
3) Skema dan termin pembayaran;
Payment scheme and terms:
• Term I : 20% uang muka
• Term II : 70% setelah equipment utama selesai dan siap kirim (before delivery)
• Term III : 5% setelah pekerjaan instalasi selesai
• Term IV : 5% setelah commissioning (serah terima)
4) Penyelesaian jika vendor tidak menyelesaikan pekerjaan sesuai yang ditentukan.
Resolution in the event the vendor fails to complete the work as specified:
Akan dikenakan penalti sebesar 0,1% per hari, atau maksimal 5% secara
keseluruhan.
A penalty of 0.1% per day shall be imposed, with a maximum of 5% of the total
contract value.
Page 9
i. Informasi mengenai tahapan yang harus dilakukan Perseroan agar stasiun LNG dapat
beroperasi komersial. Perseroan agar menyampaikan dalam lini masa berbentuk tabel
meliputi informasi tahapan beserta periode waktunya. Perseroan agar menyampaikan
informasi perbandingan tahapan yang sebelumnya disampaikan pada saat permohonan
pencatatan kepada Bursa.
Information regarding the stages that must be undertaken by the Company for the LNG
station to commence commercial operations. The Company is required to present this in
a timeline table including each stage and its corresponding period. The Company shall
also provide a comparison with the previously disclosed stages during the initial listing
application to the Stock Exchange.
m. Latar belakang dan penyebab realisasi timeline pembangunan stasiun LNG yang
disampaikan Perseroan pada saat permohonan pencatatan tidak tercapai:
Background and reasons why the realization of the LNG station construction timeline, as
submitted by the Company during the listing application, was not achieved:
1) Upaya yang dilakukan Perseroan atas tidak tercapainya rencana timeline pembangunan
stasiun LNG tersebut.
Efforts made by the Company in response to the unachieved LNG station construction
timeline.
Jawaban :
Melakukan koordinasi dan komunikasi intensif untuk dapat mempercepat proses
terbitnya alokasi gas dengan Kementerian Energi dan Sumber Daya Mineral, dan
Direktorat Jendral Minyak dan Gas Bumi.
Page 10
Answer :
Conducting intensive coordination and communication to expedite the issuance process
of gas allocation with the Ministry of Energy and Mineral Resources and the Directorate
General of Oil and Gas.
2) Dampak dan konsekuensi tidak tercapainya rencana timeline pembangunan stasiun LNG
tersebut terhadap keuangan dan operasional.
Impacts and consequences of not achieving the planned LNG station construction
timeline on the Company’s financial and operational performance.
Jawaban :
Berdampak pada proyeksi revenue perseroan di tahun 2025 untuk mencapai
pertumbuhan portofolio produk perseroan.
Answer :
This affects the Company’s projected revenue in 2025 in relation to achieving growth in
the Company's product portfolio.
3) Ada tidaknya cedera janji yang dilanggar atau wanprestasi pada perjanjian atas belum
sesuainya target waktu pembangunan stasiun LNG tersebut.
Whether there is any breach of contract or default related to the unmet timeline target for
the construction f the LNG station.
Jawaban :
Tidak adanya cedera janji yang dilanggar akibat belum sesuainya target waktu
Pembangunan LNG.
Answer :
There is no breach of contract or default arising from the unmet timeline target for the
construction of the LNG station.
n. Perizinan yang saat ini sudah diperoleh Perseroan atas pembangunan stasiun LNG.
Perseroan agar menyampaikan informasi jenis perizinan, nama instansi beserta masa
berlaku atas perizinan tersebut.
Licenses currently obtained by the Company for the construction of the LNG station. The
Company is requested to provide information on the type of license, issuing authority, and
the validity period of the license.
Jawaban :
Perseroan saat ini sedang melakukan pengurusan izin usaha niaga sementara LNG.
Answer :
The Company is currently in the process of obtaining a temporary LNG trading business
license.
Page 11
o. Perizinan yang masih dibutuhkan oleh Perseroan untuk pembangunan stasiun LNG.
Perseroan agar menyampaikan informasi jenis perizinan, nama instansi beserta waktu
yang diperlukan untuk memperoleh perizinan tersebut.
Licenses still required by the Company for the construction of the LNG station. The
Company is requested to provide the type of license, the name of the issuing authority, and
the estimated time needed to obtain each license.
Jawaban / Answer:
1) Ijin Alokasi Gas Bumi (proses di Kementerian ESDM)
Natural Gas Allocation Permit (in process at the Ministry of Energy and Mineral
Resources)
2) Ijin Lingkungan (proses di Kementerian Lingkungan Hidup)
Environmental Permit (in process at the Ministry of Environment and Forestry)
3) Ijin Usaha Sementara Niaga (proses di Kementerian ESDM)
Temporary Trading Business License (in process at the Ministry of Energy and
Mineral Resources)
4) Ijin Usaha Sementara Pengolahan (proses di Kementerian ESDM)
Temporary Processing Business License (in process at the Ministry of Energy and
Mineral Resources)
3. Sehubungan dengan penggunaan dana untuk modal kerja, agar dijelaskan:
Regarding the use of funds for working capital, please clarify the following:
a. Dampak dan manfaat penggunaan dana untuk modal kerja tersebut terhadap kegiatan
operasi dan kondisi keuangan Perseroan.
The impact and benefits of the use of funds for working capital on the Company’s
operational activities and financial condition.
Jawaban :
Dana untuk modal kerja sangat bermanfaat untuk keberlangsungan operasional
perseroan dan menunjang kondisi keuangan perseroan.
Answer :
The funds for working capital are highly beneficial for ensuring the continuity of the
Company's operations and supporting the Company's financial condition.
b. Latar belakang dan penyebab masih terdapat penggunaan dana untuk modal kerja
yang belum terealisasi.
Background and reasons why some portion of the funds allocated for working capital
has not yet been realized.
Jawaban :
Sebagai dana cadangan untuk operasional usaha perseroan.
Answer :
The funds are being held as reserves for the Company's business operational needs.
Page 12
c. Informasi mengenai rincian nama pihak yang menerima pembayaran atas
penggunaan untuk modal kerja tersebut dengan mengisi tabel berikut:
Information on the details of the parties who received payments from the use of funds
for working capital, by completing the table below:
Bentuk Skema
No Penggunaan Nilai Pembayar Pihak/Pemasok
. Dana an
1. Pembelian Gas Rp9.000.000.000 Cash Bayu Buana Gemilang
2. Pembelian Gas Rp31.932.525 Cash Bayu Buana Gemilang
3 Pembelian Gas Rp8.287.122.053 Cash Bayu Buana Gemilang
d. Informasi mengenai akun dalam laporan keuangan auditan yang merefleksikan
penggunaan dana untuk modal kerja beserta saldonya per 31 Desember 2024.
Information on the accounts in the audited financial statements that reflect the use of
funds for working capital, along with their balances as of 31 December 2024.
Jawaban :
1) Penggunaan dana terdapat pada akun Beban Pokok Pendapatan, Aset Tetap
2) Saldo per 31 Desember 2024 terefleksikan pada saldo Kas Bank di rekening
perseroan yang tercantum pada Laporan Keuangan
Answer :
1) The use of funds is recorded under Cost of Revenue and Fixed Assets accounts
2) As of 31 December 2024, the balance is reflected in the Company’s Bank Cash
account as presented in the Financial Statements
e. Dalam hal penggunaan dana untuk modal kerja tersebut dibayarkan melalui
mekanisme pembayaran uang muka, agar disampaikan informasi mengenai tanggal
pembayaran, realisasi dan perjanjian yang mendasari atas pembayaran tersebut
dengan mengisi tabel berikut:
In the event that the funds for working capital were disbursed through an advance
payment mechanism, please provide information on the payment date, realization, and
the underlying agreements for the payment by completing the table below:
Jumlah Tanggal Nilai Jangka
No Nama Pembayar an Pembayar waktu
terealisa si
. Pihak an target
realiasi
1. Bayu Buana Rp9.000.000.000 5 Januari 2024 Rp9.000.000.000
Gemilang
2. Bayu Buana Rp31.932.525 5 April 2024 Rp31.932.525
Gemilang
3. Bayu Buana Rp8.287.122.053 30 April 2024 Rp8.287.122.053
Gemilang
Page 13
f. Perseroan agar menyampaikan informasi mengenai perjanjian antara Perseroan
dengan pihak penerima uang muka, meliputi informasi:
The Company should provide information regarding the agreement between the
Company and the recipient of the advance payment, including the following
information:
1) Informasi mengenai kontrak yang ditandatangani oleh Perseroan dengan para
pihak tersebut, Perseroan agar menyampaikan dokumen perjanjian pemesanan
tersebut.
Information on the contract signed by the Company with the relevant parties, the
Company should provide the order agreement document.
Jawaban / Answer:
PT. GT Ladang Teknik
Alamanda Tower 22nd floor
Jl. TB Simatupang Kav 23 – 24
Jakarta Selatan 12430
2) Jangka waktu perjanjian.
Contract duration.
Jawaban / Answer:
18 (delapan belas) bulan sejak tanggal surat pesanan dikeluarkan.
18 (eighteen) months from the date the order letter is issued.
3) Hak dan kewajiban masing-masing pihak.
Rights and obligations of each party.
Jawaban / Answer:
Memastikan bahwa peralatan dalam surat pesanan terpenuhi.
Ensure that the equipment listed in the order letter is fulfilled.
4) Nilai kontrak atau perjanjian.
Contract value.
Jawaban / Answer:
Rp3.500.000.000 (Tiga Milyar Lima Ratus Juta Rupiah)
IDR 3,500,000,000 (Three Billion Five Hundred Million Rupiah)
5) Klausa pembatasan maupun pembatalan beserta konsekuensinya.
Limitation clauses and cancellation clauses along with the consequences.
Jawaban / Answer:
Surat Pesanan tidak mengatur klausal pembatalan dan konsekuensinya.
The Order Letter does not include cancellation clauses or their consequences.
Page 14
4. Sehubungan dengan penggunaan dana hasil konversi waran seri I, agar dijelaskan:
Regarding the use of funds from the conversion of Series I Warrants, please provide
the following information:
a. Informasi mengenai jumlah dana yang diterima Perseroan dari hasil konversi waran
seri I.
Information regarding the amount of funds received by the Company from the
conversion of Series I Warrants.
Jawaban:
Jumlah dana yang diterima oleh Perusahaan melalui konversi waran seri I adalah
sebesar Rp3.501.950 (Tiga Juta Lima Ratus Satu Ribu Sembilan Ratus Lima Puluh
Rupiah).
Answer :
The amount of funds received by the Company from the conversion of Series I
Warrants is IDR 3,501,950 (Three Million Five Hundred One Thousand Nine
Hundred Fifty Rupiah).
b. Informasi mengenai penggunaan dana yang diterima dari hasil konversi waran seri
I.
Information regarding the use of funds received from the conversion of Series I
Warrants.
Jawaban :
Dana hasil konversi dari waran seri I terdapat pada rekening perseroan.
Answer :
The funds from the conversion of Series I Warrants are held in the Company's
account.
c. Informasi mengenai pelaporan yang telah dilakukan Perseroan atas adanya
penerimaan dana hasil konversi waran seri I.
Information regarding the reporting the Company has done on the receipt of funds
from the conversion of Series I Warrants.
Jawaban :
Pelaksanaan konversi waran sejak tanggal 8 Januari 2024 sampai dengan tanggal
8 Januari 2025 sejumlah 70.039 saham.
Answer :
The conversion of the warrants was carried out from January 8, 2024, to January 8,
2025, amounting to 70,039 shares.
Page 15
d. Latar belakang dan penyebab rendahnya jumlah konversi waran seri I Perseroan.
Background and reasons for the low number of Series I Warrants converted by the
Company.
Jawaban :
Karena harga exercise waran seri I lebih tinggi (Rp 306) dibandingkan dengan
harga saham CGAS di pasar regular.
Answer :
Because the exercise price of Series I Warrants is higher (IDR 306) compared to
the price of CGAS shares on the regular market.
e. Dampak rendahnya jumlah konversi waran seri I tersebut terhadap kegiatan
operasional dan kondisi keuangan Perseroan.
The impact of the low number of Series I Warrants converted on the Company's
operations and financial condition.
Jawaban :
Tidak berdampak secara signifikan pada kegiatan operasional dan kondisi
keuangan perseroan, karena nilainya tidak material.
Answer :
It does not significantly impact the Company's operations and financial condition,
as the value is not material.
5. Sehubungan dengan kondisi keuangan Perseroan, agar dijelaskan:
In relation to the Company's financial condition, please explain:
a. Strategi Perseroan untuk meningkatkan profitabilitas.
The Company’s strategy to improve profitability.
Jawaban :
1. Melakukan efisiensi biaya
2. Melakukan penyesuaian harga penjualan
3. Menambah volume penjualan dengan adanya konsumen baru
Answer :
1. Implementing cost efficiency measures
2. Adjusting selling prices
3. Increasing sales volume through the acquisition of new customers
b. Latar belakang dan penyebab terjadinya kenaikan uang muka operasional Perseroan
dari Rp330,42 juta menjadi Rp36,94 miliar.
Background and cause of the increase in the Company's operational advance payments
from IDR 330.42 million to IDR 36.94 billion.
Page 16
Jawaban
Kenaikan uang muka operasional diperuntukkan bagi pembelian peralatan untuk proyek
distribusi LNG.
Answer
The increase in operational advance payments was allocated for the purchase of
equipment for the LNG distribution project.
c. Informasi mengenai sumber dana yang digunakan untuk pembayaran uang muka
operasional Perseroan tersebut.
Information regarding the sources of funds used for the Company’s operational advance
payments.
Jawaban
Sumber dana yang digunakan berasal dari hutang bank dan dana internal Perseroan.
Answer
The funds were sourced from bank loans and the Company's internal funds.
d. mengenai rincian uang muka tersebut berdasarkan nama pihaknya dengan mengisi tabel
berikut:
Regarding the details of the advance payments based on the name of each party, please
complete the following table:
No Jumlah Tanggal Nilai Jangka waktu target
Nama Pihak Pembayar an Pembayaran terealisasi realiasi
.
1. Sinoma Scince
9.603.118.000 2 April 2024 9.603.118.000 -
Technology
2. Sicom S.R.L 1.123.771.400
5 Desember
1.123.771.400 -
2024
3. Delta Compresion
1.281.293.550
10 Januari
1.281.293.550 -
S.R.L 2024
4. PT GT Ladang
2.949.465.560 21 Maret 2024 2.949.465.560 -
Teknik
5. Bayu Buana
21.989.925.569 30 April 2024 21.989.925.569 -
Gemilang
e. Informasi terkini atas realisasi pembayaran uang muka tersebut
Latest information on the realization of the advance payments
Jawaban :
Pembayaran uang muka sudah terealisasi.
Answer:
The advance payments have been realized.
f. Informasi mengenai kebijakan dan prosedur atas batas waktu pelaporan
pertanggungjawaban atas pembayaran uang muka operasional Perseroan
Information regarding the policy and procedure on the deadline for reporting
accountability for the Company’s operational advance payments
Page 17
Jawaban :
Pertanggungjawaban atas pembayaran uang muka operasional Perseroan dilakukan
pada saat proyek distribusi LNG dan CNG Station Grobogan beroperasi.
Answer :
The accountability for the Company’s operational advance payments will be reported
upon the commencement of operations of the LNG distribution project and the CNG
Station in Grobogan.
LAINNYA (Disampaikan kepada Publik)
OTHERS (Disclosed to the Public)
1. Rencana tindakan korporasi dalam periode 12 bulan ke depan (jika ada)
Corporate action plan within the next 12 months (if any)
Jawaban / Answer:
a. Tidak ada tindakan korporasi
No corporate actions planned
b. Perseroan dalam 12 bulan ke depan fokus pada pengembangan area distribusi
dan segmen pelanggan perseroan
The Company will focus on expanding its distribution areas and customer
segments over the next 12 months
2. Penjelasan mengenai informasi/kejadian penting lainnya yang material yang akan
dilakukan Perseroan pada masa yang datang dan dapat mempengaruhi
kelangsungan hidup Perseroan
Explanation of other material information/events that the Company will undertake in
the future and that may affect the Company’s going concern
Jawaban / Answer:
Tidak ada
None
Names mentioned 24 people and organisations named in the text · linked when the evidence is strong
unresolved
org
Bank Muamalat
p.2 ×2
unresolved
org
Bank Pembangunan Daerah Jawa Barat
p.2 ×4
unresolved
org
Bank Negara Indonesia. Subsequently
p.3
unresolved
org
PT Pertamina EP
p.5 ×2
unresolved
org
Kementerian Energi dan Sumber Daya Mineral. Answer
p.5
unresolved
org
Ministry of Energy and Mineral Resources.
p.5 ×3
unresolved
org
PT GT Ladang Teknik
p.5 ×5
unresolved
org
PT Galileo Technologies. Information
p.6
unresolved
org
PT Galileo Technologies.
p.6
unresolved
org
PT. GT Ladang Teknik Alamanda Tower
p.7 ×2
unresolved
—
Uran Tumborang
· Director
p.7
unresolved
org
Kementerian Energi dan Sumber Daya Mineral
p.9
unresolved
org
Kementerian ESDM
p.11 ×3
unresolved
org
Kementerian Lingkungan Hidup
p.11
unresolved
org
Ministry of Environment and Forestry
p.11
unresolved
org
Ministry of Energy
p.11 ×2
unresolved
—
Pembayar an
· Nama Pihak
p.16
unresolved
org
PT GT Ladang
p.16
Extraction attempts how the parser did, and what it refused
Nothing structured was extracted from this document — the attempts below say why.
No extraction attempted yet.