BERITA ACARA SERAH TERIMA PEKERJAAN
Kepada : PT Lavender Bina Cendikia
Lokasi : Perkantoran Taman Melati lantai 5
Tanggal : 31 Agustus 2024
Dengan hormat,
berikut progras hasil pengerjaan renovasi
No pekerjaan Q Unit Bobot Progres Penyelesaian
facade
1 lampu spotlight 4 set 0,25% 100% 0,25%
2 kursi panjang dengan rak sepatu (termasuk lampu LED) 6 m2 1,70% 100% 1,70%
Interior
3 logo interior 1,0 set 0,67% 100% 0,67%
4 refinishing pantry besar 1,0 set 1,01% 100% 1,01%
5 Meja receptionist refinishing 1,0 set 0,54% 100% 0,54%
6 panel dinding plywood+akrilic mirror mozaic 50,0 m2 11,21% 100% 11,21%
7 Nama-nama ruang (plateslot on partition glass) 1,0 ALL 0,45% 100% 0,45%
8 meja+4kursi set CUSTOM ruang kelas (termasuk M/E outlet) 4,0 set 7,21% 100% 7,21%
9 meja+kursi set CUSTOM workstation (termasuk M/E outlet) 4,0 set 7,21% 100% 7,21%
10 partisi Kaca+stiker 15,7 m2 4,35% 100% 4,35%
11 kursi bar 8,0 buah 1,08% 100% 1,08%
12 lampu gantung +kabel 17,0 buah 1,65% 100% 1,65%
13 lampu spotlight(kabel+lampu inbow) 40,0 buah 1,43% 100% 1,43%
14 stopkontak baru (kabel+outlet outbow) 33,0 buah 1,56% 100% 1,56%
15 saklar baru (kabel+outlet) 11,0 buah 0,43% 100% 0,43%
16 meja marmer 7,0 m1 2,02% 100% 2,02%
17 Cat interior dinding 357,0 m2 3,22% 100% 3,22%
18 lemari kabinet custom semua ruangan 36,24 m2 11,73% 100% 11,73%
19 proyektor dan layar 1,0 set 1,71% 100% 1,71%
20 Glass WhiteBoard dengan panel plywood dan hidden lamp 5,0 set 3,08% 100% 3,08%
21 lantai karpet r kelas dan kantor 121,7 m2 5,11% 100% 5,11%
22 lantai parket r kantor 70,2 m2 2,72% 100% 2,72%
23 plint lantai semua ruangan 230,0 m1 1,86% 100% 1,86%
24 pekerjaan plafon gypsum+finishing cat 40 m2 1,41% 100% 1,41%
25 pekerjaan partisi gypsum 66,45 m2 2,39% 100% 2,39%
26 panel dinding kayu modern 29,7 m2 4,82% 100% 4,82%
27 furnitur ruang meeting room+lobi 1,0 ALL 5,77% 100% 5,77%
Page 2
28 furnitur ruang meeting kecil VO area 2,0 set 2,05% 100% 2,05%
29 furnitur ruang VR dan area diskusi 1,0 ALL 1,50% 100% 1,50%
30 furnitur r guru dan pindah pantry kecil refinishing 1,0 ALL 2,58% 100% 2,58%
31 furnitur dan dekor ruang studio dan powder room 1,0 ALL 7,26% 100% 7,26%
Hasil 100%
Dengan hormat, Diterima Oleh
Achmad Firdaus Wim Wicaksono
Head Project Direktur Operasional
PT Azrina Solusi Indonesia PT Lavender Bina Cendikia
Page 3
BERITA ACARA SERAH TERIMA PEKERJAAN
Kepada : PT Lavender Bina Cendikia
Lokasi : Perkantoran Taman Melati lantai 8
Tanggal : 31 Agustus 2024
Dengan hormat,
berikut progras hasil pengerjaan renovasi
No pekerjaan Q Unit Bobot Progres Penyelesaian
facade
1 cat exterior 101,2 m2 1,47% 100% 1,47%
2 lampu spotlight 6 set 0,60% 100% 0,60%
3 kursi panjang dengan rak sepatu (termasuk lampu LED) 4 m2 1,53% 100% 1,53%
Interior
4 logo interior 2,0 set 2,15% 100% 2,15%
5 Meja receptionist refinishing 2,4 m1 1,40% 100% 1,40%
6 Nama-nama ruang (plateslot on partition glass) 1,0 ALL 0,62% 100% 0,62%
8 meja+kursi set CUSTOM workstation (termasuk M/E outlet) 3,0 set 11,93% 100% 11,93%
9 stiker partisi kaca 62,3 m2 6,70% 100% 6,70%
10 lampu gantung +kabel 12,0 buah 1,88% 100% 1,88%
11 lampu spotlight(kabel+lampu inbow) 30,0 buah 1,74% 100% 1,74%
13 saklar baru (kabel+outlet) 4,0 buah 0,25% 100% 0,25%
14 meja marmer 4,0 m1 1,86% 100% 1,86%
15 Cat interior dinding 186,0 m2 2,71% 100% 2,71%
16 lemari kabinet custom semua ruangan 24 m2 13,63% 100% 13,63%
17 proyektor dan layar 2,0 set 5,52% 100% 5,52%
18 Glass WhiteBoard dengan panel plywood dan hidden lamp 1,0 set 2,49% 100% 2,49%
19 lantai karpet r kelas dan kantor 396 m2 26,88% 100% 26,88%
20 sofa set ruang VIP 1,0 ALL 4,54% 100% 4,54%
21 plint lantai semua ruangan 120,9 m1 1,58% 100% 1,58%
22 furnitur set ruang komisaris 3,0 set 10,51% 100% 10,51%
Hasil 100%
Dengan hormat, Diterima Oleh
Achmad Firdaus Wim Wicaksono
Head Project Direktur Operasional
PT Azrina Solusi Indonesia PT Lavender Bina Cendikia
Names mentioned 3 people and organisations named in the text · linked when the evidence is strong
unresolved
org
PT Lavender Bina Cendikia Lokasi
p.1 ×2
unresolved
org
PT Azrina Solusi Indonesia
p.2 ×2
Extraction attempts how the parser did, and what it refused
Nothing structured was extracted from this document — the attempts below say why.
No extraction attempted yet.